Managing risk with the NASA Risk Matrix
Managing risk with the NASA Risk Matrix
By Anne-Laure Le Cunff • Reading time: 9 minutes
“It’s not rocket science!” people often say. Well, sometimes, projects can be so complex, making the right decision does feel akin to rocket science. Who better to turn to than one of the biggest space agencies in the world to learn how to manage risk? There are few organizations working on projects as complex as the ones NASA deals with.
NASA is known to have a process for everything. They use a standardized test to measure creativity, have detailed checklists for each project, and have developed what they call the Risk Matrix to identify and manage risk.
In their own words, the NASA Risk Matrix is “a graphical representation of the likelihood and consequence scores of a risk.” The Guidelines for Risk Management document outlines how to use the Risk Matrix for risk management. But first, you need to identify and clearly state a potential risk.
Frederick Wilcox.
How to clearly state a risk according to NASA
Condition.
The current key fact-based situation that is causing you concern, uneasiness, doubt, or anxiety.
Departure.
The undesired potential change from the original plan, which is made more likely as a result of the condition you identified.
Asset.
The project affected by the risk you identified.
Consequence. The potential negative impact the risk can have on the asset.
In addition to the risk statement, it is also helpful to include the key circumstances around the risk, the contributing factors, and related information such as what, where, when, how, and why. NASA calls all this additional information the context statement. “The context statement should include only facts, not assumptions. Ensure that no new risks are introduced here,” they explain.
What is missing from the risk statement and the context statement is a risk quantification: how likely is the consequence of the risk? For this, we need to turn to the NASA Risk Matrix.
Using the NASA Risk Matrix to quantify risk
On the y axis, you can see the likelihood, which is rated from 1 at the bottom to 5 at the top. On the x axis, we measure the consequence, which is also rated from 1 on the left to 5 on the right. So how do you rate both of these factors exactly?
For the likelihood score, you estimate how certain you are the risk will materialise.
- Not likely (under 20% probability of happening)
- Not very likely (between 20% and 40% probability)
- Likely (between 40% and 60%)
- Highly likely (between 60% and 80%)
- Near certainty (over 80% probability)
Then, for the consequence score, you use the consequence scorecard:
The consequence scorecard is great to understand the principles behind determining a consequence score. Once you are familiar with it, you can decide on a score based on your expertise and your general knowledge of the project.
Okay, let’s go back to our ebook example:
Second, what is the consequence score? Delaying the launch by a week because of the illustration work seems to fit with “Delay on some tasks minimally impacting overall schedule” in our consequence scorecard. So that would be a consequence score of 3.
Mitigating risk based on a specific NASA risk score
Lowest risk. This is the dark green area in the matrix. If your risk scores fall in this area, put the risks on a watch list and re-assess them regularly. “There is no specific requirement to generate a mitigation plan. The only requirement is to identify and track the risk drivers to ensure the risk remains tolerable,” says NASA.
Low risk. Perform extra research to better understand the risk. Write a risk mitigation plan which captures the actions to be taken to reduce the likelihood of the risk happening. Share it with your team so everyone is aware of the plan should the risk happen.
Medium risk. In addition to writing and sharing the risk mitigation plan, perform continuous risk assessments, and assign adequate resources.
High risk. Risks that have a high score need to be communicated to the NASA Independent Verification and Validation department. For you, it means high risk situations need to be escalated internally. Don’t keep these just to yourself or your immediate team. Let all relevant stakeholders know about the risk.
Highest risk. At this level of risk, you and your team may consider considerably changing the original plan. This decision may involve significant costs—in terms of schedule, performance, budget—that may be extremely difficult or even impossible to avoid. Knowing that you are dealing with the highest risk level will help in making hard but necessary choices.
It’s important to note that a mitigation plan can be to not mitigate the risk. For instance, in the case of our ebook, a mitigation strategy could be to hire another illustrator to do the job and launch on time. However, if hiring a new designer significantly impacts the overall production cost of the ebook, and results in much lower margins, it may be a smart decision to just delay the launch.
Again, you will probably not need to follow such a formal process every time you evaluate a risk, but the NASA Risk Matrix is a good mental model to use when facing uncertainty. Study it, make it yours, and use its general principles in complex situations.
Source: NESS LABS
ACER Laptop Repair near me
ASUS Laptop Repair near me
DELL Laptop Repair near me
HP Laptop Repair near me
Gateway Laptop Reapir near me
Lenovo Laptop Repair near me
SONY Laptop Repair near me
TOSHIBA Laptop Repair near me
MSI Laptop Repair near me
Alienware Latpop Repair near me
Fujitsu Laptop Repair near me
MacBook Laptop Repair near me
SAMSUNG Laptop Repair near me
Republic of Gamers Laptop Repair near me
Gaming Laptop Repair near me
Our Office
7545 Irvine Center Drive #200
Irvine, CA 92618, USA
Just around the corner from Irvine Spectrum
Contact Us
(949) 478-1502
Email Us
Office Hours
Mon-Fri: 9am – 7pm
Sat: 10am – 2pm
Sun: Closed